Project Information:
Location: Sagamore Drive in Louisburg, North Carolina
Contract Value: $850,000
Date: May 7th, 2019
Job: Remove and replace Sagamore Drive Bridge
Owner: Lake Royal Property Owners Association
Project Manager: Justin Timmons
Superintendent: Chris Hammonds
This project was located in the Lake Royle community just north of Raleigh. Dellinger was tasked with replacing the failing bridge on the north side of the community in a expedited fashion due to the amount of traffic that this structure supported daily. Dellinger replaced the existing structure with a 110’ cored slab bridge over the lake. This project was important to the community since there was only two ways to access the other half of the property and one being the structure that Dellinger was replacing.